Formula

Earn Value Formulas

PV (Planned Value) = BCWS (Budgeted Cost of Work Scheduled
EV (Earned Value) = BCWP (Budgeted Cost of Work Performed)
AC (Actual Cost) = ACWP (Actual Cost of Work Performed)
SV = EV – PV (minus is behind schedule)
CV = EV – AC (minus is over budget)
SPI = EV/PV (Less than 1 is behind schedule)
CPI = EV/AC (Less than 1 is over budget)
EAC = AC + (BAC-EV) Use when variances are atypical
EAC = AC + [(BAC-EV)/CPI] Use when variances are typical
(Note: This is the same as EAC = BAC/CPI)
VAC = BAC – EAC
ETC = BAC – EV Use when variances are atypical
ETC = (BAC – EV)/CPI Use when variances are typical
ETC = EAC – AC Use when original estimates were flawed


Project Selection Financials

NPV (Net Present Value) = FV/(1+r)n
FV= Future Value, r= interest rate, n= no. of time periods
Higher NPV is better
IRR (Internal Rate of Return) = Solve the NPV equation for “r”
Also called Hurdle Rate
Higher IRR percentage is better
BCR (Benefit/Cost Ratio)
Higher BCR is better.
Beware, exam can call it CBR, where lower is better
ROI (Return on Investment) = Earnings/Investment
Higher ROI is better
Payback Period = Time to recover cost of the project
Lower payback period is better
Cash Flow = Cash In – Cash Out

Network Diagram

Precedence Diagramming Method (PDM)

Also called Activity on Node (AON): Activities are in boxes
Most commonly used today
Has 4 relationships: F-S, S-S, F-F, S-F
No “dummies” (zero duration dependencies) allowed
Can analyze using either Three-Point Estimates or CPM


Arrow Diagramming Method (ADM)


Also called Activity on Arrow (AOA)
Only 1 relationship: F-S
Can have “dummies”
Can analyze using either Three-Point Estimates or CPM


Graphical Evaluation and Review Technique (GERT)


Allows loops and repetitive activities


Calculating Stackor Float

Total Float (also called Slack, Float, or Project Float) is the total amount of time an activity can be delayed without delaying the project finish date.
Free Float/Slack is the amount of time an activity can be delayed without delaying its successor (following activity).

LS – ES: Calculates slack with forward pass
LF – EF: Calculates slack with backwards pass

Lag Time: Inserted wait time between activities

Lead Time: Overlapping activities, also called paralleling or fast tracking.

“Lead In; Lag Out”




Three Point Estimates, or PERT

PERT = PROGRAM Evaluation and Review Technique
Holds schedule and lets cost float
3 estimates for each task: Optimistic, Pessimistic, and Most Likely
Mean Estimate = (O + 4*ML + P)/6
Standard Deviation (s) = (P – O)/6
Variance = s2 , or [(P – O)/6]2
Standard deviation of tasks on CP = Sum of variances




Accuracy of Estimates

Order of Magnitude:-25% to +75%
Budget Estimate:-10% to +25%
Definitive Estimate:-5% to +10%




Powers of a Project Manager

1. Expert: Best, earned on your own
2. Reward: Next best. Based on PM position
3. Formal: Power, based on PM position
4. Referent: Referring to positions of others
5. Penalty: Worst. Based on PM position

Conflict Resolution (Best to Worst)

1.Problem Solving: Also called Confronting
2. Compromising: Solutions satisfy both parties
3. Withdrawal: Postponing a decision
4. Smoothing: Emphasis on agreement
5. Forcing: One viewpoint at expense of another.

Sources of Conflict (Order of Priority)

1. Schedules
2. Project Priorities
3. Resources
4. Technical Opinions
5. Administrative Procedures
6. Cost
7. Personality


Herzberg’s Motivators

1. Achievement
2. Recognition
3. Challenge of the work itself
4. Responsibility
5. Advancement
6. Growth


Channels of Communication

Between Team Members = N(N-1)/2


Closing

Project is closed when administrative closure is complete.
Administrative closure is done at end of each Project Phase and at the end of the Project.
Contract closure: verification that deliverables were acceptable; it is done once at the end of the contract.
Contract Closure Procedure is produced under “Close Project”